The northwest quadrant of Maple and Washington was a parking lot for the Church on the south side of Washington and a couple of small buildings.
Street View, Sep 2018

The developer made a deal with the church that they would build extra spaces in their parking garage so that the church would not loose any parking capacity if they sold them the land. I think the church members were even supposed to get the best spaces in the garage. I wonder if they will be able to park their busses in the garage. The village parking garage is along the northwest wall of the construction. So if I go up to the fourth floor, I can get a good view of some of the construction. Another vantage point is on the east side of Washington. Although they installed a fence so that view is now harder to capture. Fortunately, my new camera has a tilt able viewscreen so that I can hold the camera over the fence.
Satellite

The purpose of this post is to provide some context for my YouTube videos of this construction. I'm way behind in editing and uploading videos because my Industrial History and Towns and Nature blogs are of higher priority. But rather than fall further behind, I've decided to post the videos out of chronological order. I'll add a link in this post in the proper chronological position when I upload a video so that this post will end up being a chronological index of the videos. 

20220517:  A "Front Shovel" Used as a Crane

20220517:  Loading Counterweights on a Grove TMS9000

20220524:  Potain Tower and TMS 9000 Cranes

22020602, 11am: TMS9000 installing precast wall panels and tower crane unloading drywall 

20220602 1:20 and 22020531: Installing floor modules

20220602, 6:20pm: Extending the boom of a TMS9000 to place the final floor slab